Zambia lacked mature large-scale tissue production lines. Local supply depended heavily on imported finished products, which caused high logistics costs, unstable delivery and limited product options. This created a clear first-mover advantage for local production.
The client had no prior tissue paper production experience. The project required full support from equipment matching, installation, commissioning to operator training, to minimize trial-and-error costs and shorten the launch cycle.
Sourcing rewinding, cutting and packaging machines from different suppliers would bring high compatibility risks. Poor matching between processes would lead to low overall line efficiency, high failure rates and difficult after-sales coordination.
Before shipment, our team provided factory layout drawings, power and gas configuration requirements, and raw material selection guidance to help the client complete workshop preparation in advance. All machines went through full load testing in our factory to ensure stable performance upon arrival.
We dispatched senior technicians to the client’s factory in Zambia to complete equipment assembly, electrical connection and full-line debugging. The team optimized process parameters based on local raw material characteristics until the entire line ran stably at standard capacity.
After full commissioning, the production line entered stable mass production and delivered clear market and operational results:
| Indicator | Before Project (Local Import Status) | After Deployment (Local Production) | Improvement / Value |
| Supply model | 100% finished product import | Full local in-house production | Eliminated long import lead times |
| Stable daily output | N/A | 9–11 tons per 8-hour shift | Filled local large-scale production gap |
| Product range | Limited imported SKUs | Toilet rolls + kitchen towel, multiple specifications | Expanded local product options |
| Unit product cost | High cost with shipping & duties | ~35% lower than imported equivalent | Strong local price competitiveness |
| Market delivery cycle | 40–50 days import cycle | Same-day / next-day local delivery | 95% faster order fulfillment |
| Project launch cycle | Long self-preparation cycle | Put into production within scheduled timeline | Fast market entry for first-mover advantage |
Contact us today to get a free customized tissue paper production line solution and detailed investment budget for your project. Share your target output and local market conditions, and our technical team will design the most cost-effective configuration and ROI plan for you.